* Seven of these projects received the coveted WBC Craftsmanship Award. This management team has proven itself capable of completing the most difficult projects in the Washington, DC area at the highest level of craftsmanship.
Complete HVAC Renovation of a 120,000 SF O.B., Fully Occupied during construction, Value $6,200,000
The Chevy Chase Land Company
Replaced central boiler plant and apartment fan coil units in occupied DCHA project. Work included replacement of piping, pumps, and controls systems upgrade. Approx. value $1,000,000
DC Housing Authority
Installation of Leak and Heat Detection systems on fuel oil piping. Also upgraded Veeder Root system. Approx value $230,000
The World Bank
Installation of Leak and Heat Detection systems on fuel oil piping. Also replaced fuel oil transfer pumps. Approx value $154,000
The World Bank
Upgrades for two floors of World Bank leased space of occupied building. Work included upgrades on AHU's including duct heaters, humidification, and controls in addition to ductwork revisions. Approx. value $200,000
The World Bank
Mechanical renovation of the National Press Building. Work included cooling towers, seventeen roof top units, replacement of interior A/C units and ductwork, controls, sprinkler, electrical, ceilings, roofing, etc. Building continued to operate 24/7 during construction. Approximate value $5,000,000
Quadrangle Development
Replacement of shut off and balancing valves for heating and cooling risers to allow proper isolation of heating and chilled water risers. Work done during off hours in occupied building. Approx. value $255,000
The World Bank
Removal of piping and ductwork from the ceiling so that structural reinforcing could be applied. After the structural reinforcing was applied, we reinstalled the piping and ductwork. The building was fully occupied during the construction. Approx. value $650,000
IMF
Upgrade of Plumbing and HVAC in the World Bank's central Fitness Center. Approximate value $100,000
The World Bank
Turnkey project to install three new cooling towers to supplement existing cooling towers includeing new supporting Approx. Value 1,500,000
The World Bank
Replace all 82 AHU's in an occupied building. All units were replaced after working hours and was completed in twelve months. Approx. value $2,400,000
The World Bank
Renovation of a tenant space for a new photo lab in NGS's DC Headquarters. Approx. value $230,000.
National Geographic
Renovation of Tenant Space. Approx. value $600,000
The World Bank
Replacement of existing AHU's while the office building remained fully occupied. Approx value $1,100,000
Spaulding & Slye
Classified
US Government
Replacement of three existing AHU's while the building remained fully occupied. Approx. value $900,000
National Geographic
Elevator Lobby and restroom renovation while the office building remained dully occupied. Approx. value $125,000
Glenborough Realty
Complete renovation of an existing DC public indoor pool. Approx. value $800,000
DC Govt. / Nat. Parks & Rec.
Renovation of existing banquet room while the building remained operational. Approx. value $40,000
University Club, Washington, DC
Replacement of existing AHU's while office building remained occupied. Approx. value $1,4000,000
The World Bank
Renovation of existing Mechanical Rooms in three fully occupied office buildings. Scope included refurbishing nine AHU's, domestic booster pumps, fan, etc. Approx. value $1,000,000
Quadrangle Development
Classified
US Government
Design/Build project to renovate existing kitchen in the Officer's Club while occupied. Approx. value $130,000
US Government
Design/Build project to renovate a tenant space for an new Print Plant. Approx. value $250,000
US Government
Modernization of HVAC and Plumbing Services in IRS Main Headquarters in downtown DC with building fully occupied. Approx. value $12,500,000.
US Government
Design/Build and install new steam boiler and humidifier system. Approx. value $1,600,000
The World Bank
Replace fifteen Computer Room A/C units while room was fully occupied and operating. Approx. value $800,000. Construction team was selected to do this project after a thorough search as conducted to find a contractor that the owner trusted with a Data Center that would cost the World Bank $75,000 per minute if the center lost cooling and went off line.
The World Bank
Replace three 1000-ton chillers, four 800-ton cooling towers, pumps and piping. Approx. value $3,000,000
US Government
Replace two 1000-ton chillers and chilled water and condenser water pumps. Approx. value $1,300,000
US Government
Replace two 250-ton Carrier Chillers and five HW Boilers, including new piping, pumps, and heat exchanger. Approx. value $1,000,000
The World Bank
Replace two 600-ton Carrier Chillers and three 400-ton Cooling Towers including piping and Chilled Water and Condenser Water Pumps. Approx value $1,400,000
The World Bank
Replaced six very large AHU's on a compressed schedule in an occupied building. Approx. Value $400,000
The World Bank
Term Contract work performed from 1994-2009 (average of 250 project per year), each ranging in value from $100 to $1,000,000
The World Bank